Demolition and a different kind of farm are changing the …
WLFI file photo
WLFI file photo
Updated: Friday, 30 Nov 2012, 3:46 PM EST
Published : Friday, 30 Nov 2012, 12:28 PM EST
WINDFALL, Ind. (AP) - Construction crews are hustling to beat a Dec. 31 deadline to finish 125 turbines for a wind farm that is eventually planned to reach into four central Indiana counties.
Project developer E-on Climate & Renewables needs to have the turbines up and running before current federal tax credits for wind energy expire.
Crews are working overnight to finish building 69 turbines in eastern Tipton County and 56 in northern Madison County. Project manager Andy Melka tells the Kokomo Tribune that crews are only working at night because the winds are calmer.
He says 75 of the electricity-generating turbines have been completed. Nearly 200 more turbines are planned in Howard and Grant counties in later phases.
Comments WLFI.com is migrating to a more stable commenting system called DISQUS. This system is used by CNN, TIME, FOX News, numerous blogging sites and has over 75 Million registered users. Unfortunately we can't migrate our current user accounts to this new system.
To sign up for a DISQUS account, click the DISQUS button just below and to the right and then click Login.
DISQUS lets you login with several different options, including Facebook, Google, Twitter, Yahoo or OpenID. We expect it to allow more conversation and better moderation. If you have any questions, please feel free to comment below.